PHASE-||- REPAIRING ROADS FOR (AL RIFAI & AL NAJJAR) NEIGHBORHOOD – WEST MOSUL, NINEWA GOVERNORATE
Project location :Ninewa Governorate
Client :United Nations Developmen Programme - Iraq (UNDP)
Contract Value (US$) :(US$):
Contract Duration: 3 Months
Contract Start Date:2019-10-21
Contract Completion2020-03-10
Scope of work:
AL KHATAB AL MUTAHIDA Co. had been contracted with (UNDP) to Repairing Roads For (Al Rifai & Al Najjar) Neighborhood – West Mosul, Ninewa Governorate according to BoQ & Iraq's standard Specifications for road and bridges.
The contract contains the following activities:
1- Removing all the damaged asphalt layers, all rubble and debris to a dump site approved by the local authorities.
2- Leveling the bottom, watering and compaction of the base up to (95%) of MDD.
3- Supply of materials, tools, machineries and manpower for filling the excavated places beneath the asphalt pavement & over the walkways with sub base Type (A) in layers exceeding (25 cm), includes watering, and compaction of each layers up to (95%) of MDD and cleaning the surface with compressed air.
4- Replacing Damaged parts of Curbstone then provide concrete base (200*850) mm beneath the curbstone.
5- Supply of materials, tools, machineries and manpower for paving asphaltic concrete (stabilizer coarse) thickness (10 cm) after compaction and applying prime coat layer in a ratio of 1 L/ m2, compaction of the stabilizer layer up to 97% of MDD.
6- Supply of materials, tools, machineries and manpower for paving asphaltic concrete (binder coarse) thickness (6 cm) after compaction and applying tack coat layer in a ratio of 0.5 L/ m2, compaction of the binder layer up to (97%) of MDD.
7- Removing all the damaged parts of the walk way, casting (10cm thick) plain concrete using sulphate resistance cement and (C25MPa) concrete.
8- Supplying manholes, gullies & Laying of Gullies pipes.