Pavement and fixing the shoulders of Makhmur and Qarach Roads, with Length 15 KM in Mosul.

Project location :Ninawa province

Client :Republic of Iraq Ministry of Construction and Housing Department of Contracts / IRAQ

Contract Value (US$) :(US$):

Contract Duration: 1 Year

Contract Start Date:2010-11-12

Contract Completion2012-08-01

Scope of work:

The contract contains the following activities.

  1. Excavate the existed asphalt layer, reach to design elevation and with compaction degree≥95%.
  2. Scratching the existed asphalt surface.
  3. fixing the shoulders.
  4. Remove the defective asphalt concrete, replace and compact 30cm sub base, pave 10cm asphalt stabilizer
  5. Asphalt stabilizer macadam air void: 3~6%, prime coat medium-curing type cutback asphalt (MC-70).
  6. After compaction, 10cm thick asphalt stabilizer macadam air void: 3~6%, prime coat medium-curing type cutback asphalt (MC-70).
  7. Supply, transport, lay and compaction 60mm wearing course of hot mix asphalt concrete (AC-20).
  8. Road guidance sign, Guidance arrow, white color paint, Road mark line
  9. All works accordance with Iraqi standard for road and bridges.

Photos

Projects
Send us a message

Our Contacts

Address

AI-Zwyia-Baiji, Salahuddin - Iraq 126 English Village, Erbil - Iraq

Al-Mutanaby
neighborhood - Baghdad - Iraq

Al-Baradya zone - Basra - Iraq


Email

info@alkhatabco.com 

alkhatab.almutahida@gmail.com


Mobile

009647708506005

009647517106759

009647834140505