CONSTRUCTION AND PAVING ROAD LINKING THE VILLAGE OF AL- MUSTANTIQ TO THE MOSUL - BAGHDAD ROAD LENGTH 8 KM
Project location :Ninewa Governorate
Client :Ninewa Governorate - contracts section
Contract Value (US$) :(US$):
Contract Duration: 240 Days
Contract Start Date:2020-01-03
Contract Completion2020-12-01
Scope of work:
A contract was signed with (Nineveh Governorate - contracts section) to complete a project Construction and paving road linking the village of Al- Mustantiq to the Mosul - Baghdad road length 8 km, Nineveh Governorate, where our company provided a package of general civil services and works according to the contract requirements and BoQ.
The contract contains the following activities:
1- Supply of materials, tools, machineries for laying two layers under the foundation (Sub-base Type A) with spraying and compaction not less than (95%) and with a total thickness of no less than (20 cm) two layers.
2- Supplying, spreading and compacting layer from (Sub-base Type A) thickness (15 cm).
3- Laying and compaction a layer from asphalt base course thickness (10 cm) with a width of (6 m) and spraying (Prime coat).
4- Fixing the shoulders of the road by using (Sub-base Type A) thickness (10 cm) with a width of (1.5 m) for each side of the road.
All requirements according to Iraqi roads and highways technical specification